Field guide
Arc Flash Label Maker: Labels From Your Panel Data
Free tool · no sign-in
Make a label from your panel data
Enter the panel data. You get the numeric result and a watermarked label preview for free; the clean, print-ready PDF is a paid step. The clean, unwatermarked PDF is a paid step: a label pack at $19 for 10 credits that never expire (one credit covers one panel: the clean label PDF, the calculation record and the permit, re-downloadable later), or Pro at $29/mo. You sign in with an email link or Google at that point and go straight to checkout for what you picked. The method covers 208 V to 15 kV; clearing time above 2,000 ms is refused rather than shortened.
Calculation support for qualified electrical-safety workflows. Not an engineered study, not a PE seal, not a work authorization. Method, limits and validation.
Most pages that rank for "arc flash label maker" hand you a blank form or sell a roll of stock. The form above does the opposite job: you type the panel data, the engine computes the values that go on the label, and you see a watermarked render of the finished label before anything is paid for. This page explains what that form does, what is printed on the label it produces, and the points where you should stop trusting a browser tool and call a qualified engineer.
Last reviewed: November 20, 2026.
What the label maker does, step by step
- You enter eight numbers and a name. System voltage, available bolted fault current, electrode configuration, conductor gap, working distance, the clearing time of the upstream protective device at the arcing current, the clearing time at the reduced arcing current, and an equipment ID of up to 40 characters such as "MCC-2 Lineup A".
- The IEEE 1584-2018 engine runs both arcing-current branches. The standard calls for a full-current case and a reduced-current case because a lower arcing current can make a device trip more slowly, which can turn the lower-current case into the worse one. The engine reports whichever governs and flags it when the reduced case does.
- A record is stored with the engine version. The calculation is saved with its inputs, flags and the engine version string, so a number on a printed label can be traced to the version that produced it.
- You land on a preview page. It shows the numeric results, the method used, and a watermarked PDF render of the real label at 4×6 inches. The numbers are free to read and copy.
- The clean PDF is the paid step. It removes the watermark and adds the calculation record and an energized-work permit pre-filled from the same stored values. Sign-in happens at that point, with an email link or Google, and you go straight to checkout for the item you picked. The preview stays attached to your account. The pricing sentence in the form above is generated from the live checkout status, so it says "not on sale" if that is ever true.
The label sizes the clean bundle supports are 4×6 in, 4×4 in and 3.5×5 in, the three that public project specifications name most often. The older 2×3.5 in size was dropped because no specification in our research asked for it. The size comparison and the print rules live on the arc flash label template and arc flash label printer pages.
What is printed on the label
The generated label carries the fields the two governing documents ask for, laid out in an ANSI Z535-style format:
- A signal-word header and the words ARC FLASH HAZARD. The tool uses WARNING by default. IEEE 1584 does not set an automatic WARNING or DANGER threshold, so the equipment owner's documented hazard-communication policy decides which word applies.
- The equipment ID and, if supplied, a location.
- Nominal system voltage.
- Incident energy in cal/cm² and the working distance it applies to.
- The arc-flash boundary in inches and millimetres.
- The PPE selection basis: for a calculated result, a minimum arc rating equal to the incident energy; for a table-method result, the PPE category. The two are never converted into each other.
- Shock approach distances.
- Available fault current and the date it was obtained.
- A method line stating CALCULATED, IEEE 1584-2018, or TABLE METHOD, NFPA 70E.
- A label ID, report number, assessment date, and the engine version.
The assessment date matters more than it used to. As EC&M's coverage of the 2026 National Electrical Code explains, the label content in NEC 110.16 now names the date the assessment was completed. The label maker stamps the date the calculation ran, which is the assessment date only if you treat that run as the assessment. If the values came from an earlier study, the date on a label should be that study's date, not today's. Reading the field list against your own paperwork is covered in arc flash label requirements.
Where the numbers come from, and what you must supply
The engine is only as good as the two inputs it cannot check: available fault current and clearing time. Both have to come from somewhere real.
Available fault current comes from a utility letter, a short-circuit study, or an estimate from transformer size and impedance. An estimate from nameplate data is an upper bound, and a higher fault current can mean a faster trip and a lower incident energy, which is why an over-estimate is not automatically conservative. The page on available fault current explains the trap and the three ways to find the figure.
Clearing time comes from the time-current curve or trip-unit settings of the device upstream of the equipment, read at the arcing current and again at the reduced arcing current. The form asks you to tick a box confirming each time came from protective-device data. That is not decoration. A clearing time typed from memory is the most common way a clean-looking label ends up wrong. The clearing-time wizard helps you pick a defensible value when you do not have the curve open.
If you are unsure of either input, treat the output as a draft. Do not apply the label until a qualified person has checked both inputs against the real equipment.
Where the method stops
A safety label that overstates its authority is worse than no label, so these limits are enforced in code and stated here:
- Voltage window. The calculated method covers 208 V to 15 kV, matching the model range of IEEE 1584-2018. Outside it, the tool uses the NFPA 70E table method where a verified table row exists and says so on the label. Where neither applies it returns "engineering study required" and prints no number.
- Clearing time cap. Times above 2,000 ms are rejected, not shortened. A long exposure needs an engineer to decide what is reasonable.
- Working distance floor. Distances under 305 mm are raised to 305 mm and the record says so.
- Table method is not a calculation. When a table row is used, the label states TABLE METHOD and carries a PPE category and boundary from the table, with no incident-energy value invented.
- What it never does. It does not model DC systems, single-phase systems, or multiple sources and tie breakers. It does not inspect equipment condition. It does not authorise work.
NFPA 70E and IEEE 1584 are copyrighted. This page and the tool cite them and describe how the method behaves, and they do not reproduce table values or clause text. The 2018 edition of IEEE 1584 and the 2018 table method of NFPA 70E are the versions implemented. The full statement of scope is on the methodology page.
Printing the result
A label that fades is worse than none. Public project specifications that name a print method ask for machine-printed, thermal-transfer output on UL 969 adhesive stock with no field markings, and the Delaware DNREC project manual is one example. Hand-written values fail those jobs. Direct-thermal desktop printers can serve indoors for a short time but are not UV-stable. If you cannot print in-house, take the clean PDF to a sign shop that can run polyester stock. The comparison of the three routes, generic stock, custom preprinted and print-your-own, is on print your own arc flash labels.
When a label maker is the wrong tool
Use an engineering study instead when the system has multiple sources, tie breakers, large motor contribution, medium-voltage equipment beyond the model window, or protective devices you cannot read curves for. The same applies if you need a coordination review or incident-energy reduction recommendations. A per-panel label is a reasonable route for small, simple, well-documented equipment. The cost side of that decision is on arc flash study cost, and a list of what to ask a firm is on the study companies page.
Whoever produces the label, NFPA 70E expects the underlying risk assessment to be reviewed at intervals not exceeding five years and after changes that could move the numbers. Re-run the maker when a service is upgraded, a transformer is swapped or a protective device changes, then replace the label.
This tool is calculation support for a qualified person. It is not a PE seal and not an engineered study, and its output does not replace one.
Direct answers
Frequently asked questions
Is the arc flash label maker free?
Entering data, seeing the calculated values and viewing a watermarked label preview are free. The clean, unwatermarked PDF with the calculation record and permit is a paid step, and the form states the current price and availability.
What sizes can the label be?
The clean bundle supports 4x6 in, 4x4 in and 3.5x5 in, the sizes public project specifications name most often. The free preview is rendered at 4x6 in.
What goes on the label?
Signal word, equipment ID, nominal voltage, incident energy with its working distance, arc-flash boundary, the PPE selection basis, shock approach distances, available fault current and its date, the method used, the assessment date, a label ID and the engine version.
Which date does the label carry?
The date the calculation ran. That is the assessment date only if you treat the run as the assessment. If the values come from an earlier study, the label should carry that study's date.
What happens when I click Download as a guest?
You are asked to sign in with an email link or Google, then taken to checkout for the item you chose, with your preview attached to the account. Nothing is charged until you complete checkout.
When is a label maker the wrong tool?
When the system has multiple sources, tie breakers, large motor contribution, equipment beyond 15 kV, or protective devices whose curves you cannot read. Those need an engineered study.
Source trail
Sources
Standards references identify the applicable document or section where possible. Standards text may require licensed access. Report a factual issue through the process on our corrections page.